M and M Direct New Warehouse - Moreton Business Park

One of the largest projects we have undertaken, this new 80 000 ft2 warehouse for clients Great West based on Moreton business park provided an exciting and challenging task for G.P. Thomas.

“Following a successful tender process, G.P.Thomas were selected to design and build a 80.000ft sq high bay warehouse to be occupied by our tenant,M+M Direct Ltd;

The building was constructed on a live site packed with services feeding the other tenants on the business Park, ensuring that the construction process had to be carried out in an efficient and safe manner ; Good working practices were followed throughout the build process;

Work on the project started in December 2009 and continued throughout one of the worst winters for many years. No days were lost to the weather conditions, due to the work ethic of the G.P.Thomas staff and management

The project contained many challenges, not lease of which was the construction of a Class 1 super flat laser levelled floor in the warehouse;

The project was completed within budget and the building was handed over to our tenant one month early, despite the terrible weather conditions throughout the project;

We were delighted with the outcome of the project and would not hesitate in using G.P.Thomas again on future builds;”

Andrew Horner

Business development director; Great West 2003 ltd

“This was a major project where every detail really mattered. The renovation of this centuries old barn required the retention of character whilst giving it a new lease of life as contemporary offices. GP Thomas listened to our concepts and converted them in to reality. They were on our wavelength throughout and the results, despite many challenges are rather spectacular. We thank them for the care and quality of work they delivered throughout the project”

Doug Burgoyne, Director, TIOS

Back to top